In a recent case brought before the Rajasthan Real Estate Regulatory Authority (RAJ-RERA-C-N-2022-5583), Complainant A, the complainant, sought relief for delayed possession of her flat in the projects by the developer, the respondent. This article aims to provide an in-depth analysis of the case, highlighting the facts, legal proceedings, and the final order issued by Hon'ble the Authority Member, Member of the Authority.
Complainant A had entered into an Agreement for Sale with the developer on 28.12.2016, with an understanding that possession of the booked flat in the project would be handed over within 36 months from the date of the agreement, i.e., December 2019. The total consideration for the unit amounted to Rs. 39,21,220, out of which Complainant A had already deposited Rs. 36.30 lakh to the promoter.
However, despite the significant amount paid by the complainant, possession was not delivered as promised. Seeking redress, Complainant A filed a complaint under section 31 of the Real Estate (Regulation and Development) Act, 2016 (RERA Act). In addition to the refund of her deposit, Complainant A requested compensation of Rs. 10,000, reimbursement of litigation expenses amounting to Rs. 50,000, and ancillary relief.
Upon receiving the complaint, the Rajasthan Real Estate Regulatory Authority initiated the necessary proceedings. Notices were issued to the developer on 26.08.2022 and 30.09.2022, requesting a response to the complaint. However, the promoter failed to provide any response, leading to an ex-parte hearing where only Complainant A's counsel, the complainant's counsel, presented arguments and evidence in support of the complaint.
During the hearing, the Authority examined the Agreement for Sale executed between the parties, which revealed that Rs. 4.40 lakh was already paid to the promoter at the time of signing the agreement. Further payments were to be made as per the agreed installments.
A demand letter dated 22.12.2021 from the promoter indicated that an additional amount of Rs. 6.50 lakh was remitted by Complainant A. Additionally, a statement from the developer. dated 20.06.2022 confirmed a disbursement of Rs. 26,85,922 to the promoter. In total, Complainant A had paid Rs. 33,35,922 to the developer.
The project had initially set a completion date of 31.07.2019 and was registered as an ongoing project. An extension was granted until 31.07.2022. However, despite the extension, the project remained incomplete and was currently categorized as lapsed. The physical progress of the project, as reflected in the Quarterly Progress Report until March 2022, stood at only 61%.
Considering the evidence and circumstances, the Authority ruled in favor of Complainant A. The complainant's right to claim a refund in case of non-completion of the project within the specified period, as per the Agreement for Sale, was upheld.
The developer was directed to refund the deposit amount of Rs. 33,35,922 to Complainant A, along with interest at the rate of 8.6% of the highest Marginal Cost of Funds based Lending Rate (MCLR) of the State Bank of India (SBI). The interest was to be calculated from 01.01.2020, excluding any moratorium period notified by the Authority. The promoter was given a deadline of 45 days from the date of uploading the order on the Authority's webpage to fulfill the refund.
Furthermore, the order stated that if Complainant A filed an application for execution within two years, recovery proceedings would be initiated against the developer under section 40(1) of the RERA Act. The case would then be remitted to the concerned District Collector after the issuance of the Recovery Certificate.
The project case serves as an important reminder of the significance of adhering to agreed-upon timelines and delivering possession to homebuyers as per contractual obligations. The order issued by the Rajasthan Real Estate Regulatory Authority emphasizes the rights of the complainant and ensures that necessary steps are taken to secure the refund of the deposit amount.