Rajasthan RERA considered a homebuyer's refund claim arising from an incomplete housing project that had not delivered possession within the agreed timeline.
Background
The homebuyer made payments in 2015 and entered into an agreement for sale on 9 February 2016. The agreement contemplated delivery within 36 months, but the project remained incomplete after the expected possession date in June 2019.
The homebuyer sought a refund with interest, citing the prolonged delay and lack of progress.
Proceedings
During the complaint proceedings, the respondents sought additional time to file their reply. The Authority ultimately proceeded to determine the refund claim on the material available before it.
Authority's decision
Rajasthan RERA directed refund of ₹5.27 lakh. Interest was prescribed at the State Bank of India's applicable MCLR plus 2%, reflected in the source order as 9.30% at that time.
The respondents were directed to comply within 45 days and submit a compliance report thereafter.
Consequences of non-compliance
If the refund and interest were not paid within the stipulated period, the homebuyer could pursue execution and recovery under Section 40(1) of the Real Estate (Regulation and Development) Act, 2016 and the applicable rules.
Practical significance
The order demonstrates the exit remedy available to a homebuyer when a project remains incomplete well beyond the contracted possession period. It also shows how the Authority combines a refund direction with a defined interest formula and enforcement timeline.