Rajasthan RERA considered a refund claim arising from an incomplete project whose registration had entered lapsed status and where possession remained outstanding well beyond the expected date.
Background
The allottee had booked a unit in 2013. The source record showed payments of ₹5,01,913 against a total consideration of ₹5,28,330.
The allotment documentation contemplated possession in February 2016. The project was later registered as an ongoing project under RERA with a subsequent completion timeline, but remained incomplete after the extended registration period expired.
Authority's analysis
The Authority treated the allottee's refund right under Section 18 of the Real Estate (Regulation and Development) Act, 2016 as overriding a contractual clause that sought to restrict refund entitlement.
It also noted that the regulatory framework applied to the ongoing project even though the original allotment pre-dated RERA registration.
Order
The promoter was directed to refund ₹5,01,913 together with interest. The source article recorded the applicable interest rate as 8.60% per annum from 1 March 2016, subject to exclusion of any moratorium period notified by the Authority.
The refund and interest were to be paid within 45 days of the order being uploaded.
Practical significance
The order demonstrates that a lapsed and incomplete project can trigger the allottee's statutory exit rights despite contrary wording in older allotment documentation.
It also illustrates how RERA can apply to an ongoing project whose original transaction began before the regulatory registration date.