Rajasthan RERA considered a delayed-possession complaint in which the homebuyer sought to exit the transaction and recover the amount already paid.
Background
The agreement for sale was executed on 22 April 2019 and stated a possession date of 31 December 2020. The homebuyer had paid ₹32.90 lakh against a total consideration of ₹35.30 lakh.
The project's completion timeline was later extended to 31 December 2022. By the time the complaint was considered, the project had moved into the lapsed category.
Relief sought
The homebuyer sought:
- refund of the deposited amount with interest;
- compensation for litigation expenses;
- relief for alleged breach of the agreement and RERA obligations; and
- protection against further demands while the dispute was pending.
Proceedings
The promoter did not file a reply within the period provided by the Authority, and the matter proceeded ex parte on the available record.
Authority's order
Rajasthan RERA directed refund of ₹32,90,000 together with interest at 8.6% per annum from 1 January 2021, subject to exclusion of any applicable moratorium period notified by the Authority.
The refund was to be made within 45 days of the order being uploaded. Failure to comply could lead to recovery proceedings under Section 40 of the RERA Act.
The Authority also noted that the separate compensation claim fell outside the relief it was determining and could be pursued before the appropriate forum.
Practical significance
The order illustrates the refund remedy available when possession remains outstanding and the project has reached a lapsed regulatory status. It also distinguishes the Authority's refund jurisdiction from separate compensation proceedings.