Rajasthan RERA considered a complaint involving prolonged non-delivery of a unit financed partly through a housing loan.
Background
The unit was booked in June 2016. The agreement contemplated completion by 31 December 2018, with a further 12-month grace period.
The source article recorded that the allottee had paid ₹21.94 lakh, approximately 63% of the total consideration. A lender had disbursed ₹14.71 lakh under the financing arrangement.
The promoter had also undertaken to service pre-EMI amounts for a period but later stopped doing so.
Proceedings
The promoter did not appear on three consecutive occasions despite service of summons. The Authority therefore proceeded on the basis of the complainant's evidence and the documents on record.
Authority's order
The Authority found that the promised completion timeline had passed by several years and that possession was not expected in the foreseeable future.
It directed refund of ₹21.94 lakh with interest at the rate prescribed under the Rajasthan RERA rules. The source article recorded that rate as 9.30% per annum, calculated from the dates of the respective deposits until refund.
The promoter was also directed to settle outstanding liabilities with the lender so that the related loan account could be closed.
Practical significance
The order illustrates how refund relief can interact with third-party housing finance. Where a lender has funded part of the purchase price, resolving the allottee's exit from the transaction may require both repayment to the buyer and settlement of the loan-side obligations.