Rajasthan RERA considered a refund complaint where a housing project remained incomplete well after the contractual possession timeline and its regulatory registration had lapsed.
Background
The allottee had booked a residential unit and made an initial payment of ₹6.75 lakh. The historical article recorded aggregate payments of ₹49.34 lakh.
An agreement for sale dated 14 December 2016 contemplated completion within 36 months plus a six-month grace period, placing the expected possession date around May 2020.
The project remained unfinished after that date and its RERA registration had lapsed in March 2020.
Promoter's response
The promoter acknowledged receiving ₹49.34 lakh but disputed the total sale consideration stated by the allottee. It also attributed the construction delay to circumstances beyond its control and financial stress.
Authority's decision
The Authority focused on the continued non-completion of the project and the fact that possession remained outstanding more than two and a half years beyond the promised date.
It directed refund of ₹49.34 lakh together with interest at the prescribed Rajasthan RERA rate, recorded in the source article as 9.30%.
The promoter was given 45 days to comply, with a compliance report to follow. The allottee was separately advised that a compensation claim could be pursued before the Adjudicating Officer.
Practical significance
The order reinforces the statutory refund remedy where a promoter remains unable to deliver possession within the agreed period and the project itself has fallen into lapsed regulatory status.
It also distinguishes refund with interest from a separate compensation claim, which may fall within the Adjudicating Officer's jurisdiction.