Rajasthan RERA considered a dispute involving delayed project completion where the allottee had made substantial payments but an agreement for sale had not been executed.
Background
A provisional allotment had been issued in 2014 after a booking made in 2013. The source record referred to a total consideration of ₹28,45,250.
The project was initially expected to be completed by 31 January 2021 and later received an extension to 31 March 2023. A partial completion certificate for two blocks was issued on 20 March 2022.
Missing agreement for sale
A central issue was that the parties had not executed an agreement for sale. The Authority considered this significant when assessing a later payment demand, particularly because more than 25% of the consideration had already been paid.
Completed-project consideration
The Authority also took account of the completion status of the relevant blocks and the principle that refund relief may be treated differently once a project or relevant unit is complete.
The dispute therefore required a balance between delayed-completion relief and the fact that possession could still be offered.
Authority's directions
The Authority directed that a fresh demand be raised after accounting for accrued delayed-possession interest.
Interest was to be calculated at 8.6% from 31 January 2021 until the offer of possession, subject to the applicable regulatory treatment of the period concerned.
If the allottee chose not to take possession, the order contemplated deduction of administrative charges equal to 10% of the deposit, with the balance refunded together with applicable interest from 1 February 2021, excluding the notified moratorium period.
Practical significance
The order shows how RERA can fashion relief other than an immediate full refund where the project has reached completion but possession was delayed. It also highlights the importance of executing the statutory agreement for sale before substantial payment and demand obligations accumulate.