Rajasthan RERA considered a complaint concerning a developed plot where possession had remained outstanding for roughly eight years after the contractual delivery timeline.
Background
The buyer had booked a plot in 2013 and entered into an agreement for sale on 1 December 2013.
The total consideration recorded in the historical article was ₹3,85,000, of which ₹3,46,500 had been paid.
The agreement contemplated delivery of the developed plot by June 2015. The buyer later complained that possession had still not been delivered and that development commitments had not been fulfilled.
Ex-parte proceedings
The promoter did not appear despite service of summons and did not file a response to the notices issued by the Authority.
Rajasthan RERA therefore proceeded ex parte and assessed the buyer's documentary material on the available record.
Refund order
The Authority found that the paid amount had remained with the promoter for years without delivery of possession.
It directed refund of ₹3,46,500 together with interest at the rate prescribed under the Rajasthan Real Estate (Regulation and Development) Rules, 2017. The historical article recorded the applicable rate as 9.30% at the time.
The promoter was given 45 days to comply and was required to provide a compliance report thereafter.
Recovery if the order is not complied with
The order contemplated recovery under Section 40(1) of the Real Estate (Regulation and Development) Act, 2016 and the applicable rules if payment was not made within the stipulated period.
Practical significance
The order demonstrates the consequences of prolonged non-delivery combined with non-participation in regulatory proceedings.
It also illustrates that an ex-parte RERA order still rests on the material placed before the Authority: non-appearance does not remove the need to establish the payment and possession history supporting the requested relief.