Rajasthan RERA issued a common order on 20 January 2023 addressing ten complaints by homebuyers against the same promoter. The order dealt with delayed-possession interest, compensation, a statutory penalty and the mechanism for recovery.
Common directions
The Authority directed the promoter to pay interest to the respective complainants at the rate prescribed under Rule 17 of the Rajasthan Real Estate (Regulation and Development) Rules, 2017. The interest was to run from the expected delivery date stated in the relevant agreements until possession.
The individual case files were also sent to the Adjudicating Officer for determination of compensation where applicable.
Penalty and costs
The Authority imposed an additional penalty of ₹20,000 for violation of Section 13(1) of the Real Estate (Regulation and Development) Act, 2016.
It did not award the litigation or harassment costs claimed by the applicants.
Applications by the promoter
The promoter sought clarification and reconsideration of aspects of the common order. After considering those applications, the Authority maintained that the interest amounts remained payable.
A request to shield the company's directors from the recovery process was also rejected in the context of the material before the Authority.
Recovery proceedings
Because the payment directions had not been complied with, the Authority issued a recovery certificate. The order contemplated recovery as arrears of land revenue under Section 40(1) of the RERA Act and the applicable Rajasthan rules.
The Registrar was directed to issue the necessary recovery process and refer the matter to the appropriate District Collector.
Practical significance
The order illustrates how multiple complaints concerning the same promoter can be resolved through a common regulatory direction while compensation remains individually assessed. It also shows how RERA enforcement can move from an interest award to formal recovery proceedings when an order is not complied with.