Rajasthan RERA awards 8.6% delay interest and directs possession within registration period

In Complaint No. RAJ-RERA-C-N-2022-5569, Rajasthan RERA awarded 8.6% delay interest from 1 April 2021 and directed possession within the project's extended registration period

Rajasthan RERA awards 8.6% delay interest and directs possession within registration periodREUNION / INSIGHTSCLARITY / CONTEXT / PERSPECTIVE
Reunion Insights editorial image

In a significant case before the Rajasthan Real Estate Regulatory Authority (RERA), Complainant A has filed a complaint against the developer, alleging a breach of agreement for delayed possession of the booked unit in the project "the project." The complaint was filed under Section 31 of the RERA Act, with the case number RAJ-RERA-C-N-2022-5569.

The case involves an agreement for sale executed on 30.10.2017, with an expected possession delivery in March 2021, including a grace period of six months. The Complainant has paid Rs. 16.38 lakh out of the total consideration of Rs. 18.00 lakh but has not received possession within the stipulated timeframe. This article provides a detailed account of the case and the subsequent order issued by the Rajasthan RERA Authority Member.

The Background of the Complaint:

Complainant A filed the complaint against the developer, seeking possession of the booked unit in the project, which was registered with Rajasthan RERA. The agreement for sale was executed on 30.10.2017, with a promised possession date by March 2021, including a six-month grace period. The Complainant had deposited Rs. 16.38 lakh out of the total consideration amount of Rs. 18.00 lakh, but the Promoter failed to hand over the possession as per the agreed timeline.

Case Number: RAJ-RERA-C-N-2022-5569

Complainant: Complainant A

Promoter: the developer.

Date of Order: 16.02.2023

Hon'ble Member: the Authority Member

Notice and Absence of Response:

Upon filing the complaint, the developer, was served with notices on 18.08.2022 and 20.10.2022, requesting a reply to the complaint. However, the Promoter failed to submit a response within the specified period mentioned in the notice. Consequently, a notice dated 01.12.2022 was sent through the Promoter's online Dashboard, fixing the case for a hearing before the Rajasthan RERA Authority.

Adjudication and Hearing:

Despite being served notice through the online Dashboard, no representative of the developer appeared before the Authority. As a result, the Authority decided to adjudicate the matter by invoking the power empowered under Rule 35(2)(j) of the Rajasthan RERA Rules, 2017. The complainant, represented by counsel, was given an opportunity to present the case and was heard at length.

Order of the Rajasthan RERA:

After careful consideration of the arguments presented by the Complainant and examination of the available records, The Rajasthan RERA Authority Member issued the order on 16.02.2023.

Decision and Relief Granted:

The Authority observed that the project was not completed yet, and the Promoter had already sought an extension for completion, valid until 30.09.2023. The Complainant, however, insisted on receiving possession of the unit without amending the relief sought through the complaint. The Authority, taking this into account, directed the Promoter to pay interest at the rate of 8.6% (highest MCLR + 2%) from 01.04.2021 until the actual delivery of the unit to the Complainant.

Possession and Outstanding Consideration:

The Authority directed the Promoter to hand over possession of the unit to the Complainant within the validity period of registration. If the amount of accrued interest exceeds the outstanding consideration, the Promoter is required to pay the excess amount to the Complainant by the 10th of every calendar month.

Conclusion:

The case filed by Complainant A against the developer highlights the issue of delayed possession in the real estate sector. Despite the extension granted by the Authority for project completion, the Promoter failed to meet the agreed-upon possession date. The Rajasthan RERA, considering the circumstances, ruled in favor of the Complainant, directing the Promoter to pay interest and deliver possession within the registration's validity period. This case emphasizes the importance of timely delivery in real estate projects and the role of regulatory authorities in ensuring justice for homebuyers.