Rajasthan delayed-possession dispute continues after refund order is stayed by High Court

A later Rajasthan RERA complaint records that an appellate refund order for Rs. 16.80 lakh with 10% interest had been stayed by the High Court, with the promoter directed to make a Rs. 20 lakh depo...

Rajasthan delayed-possession dispute continues after refund order is stayed by High CourtREUNION / INSIGHTSCLARITY / CONTEXT / PERSPECTIVE
Reunion Insights editorial image

In a recent complaint filed under the Real Estate (Regulation and Development) Act, 2016 (RERA Act), Complainant A and Complainant B, hereinafter referred to as the "complainants," lodged a case against the developer, a prominent real estate company. The case, bearing Complaint No. RAJ-RERA-C-2022-5271, revolves around allegations of delayed possession and seeks compensation for the inconvenience caused to the complainants.

Background:

Complainant A and Complainant B booked the booked unit with a super area of 750 sq.ft. in "Tower D" of a group housing project developed by the developer. The total sale consideration for the flat was Rs. 18,46,200/-, excluding taxes. The agreement for sale was executed on June 23, 2017, with a project completion timeline of 36 months plus a grace period of 6 months from the date of agreement.

Details of the Complaint:

The complainants alleged that despite the agreed-upon timeline, the possession of the flat was not delivered as per the scheduled deadline of 23.12.2017, inclusive of the grace period. They further claimed that an offer letter was finally given to them on 01.06.2020, which indicated a significant delay in the project's completion and possession handover.

In response to their grievances, the complainants filed a complaint, numbered 2019-3320, before the Rajasthan Real Estate Regulatory Authority. Their complaint sought a refund of the amount paid, along with interest and compensation. The Authority, in its order dated 28.12.2020, directed the respondent (the developer.) to pay interest at the prescribed rate from 01.01.2017 (later rectified to 01.01.2018) till 31.05.2020. However, the Authority granted liberty to the complainants to approach the appropriate forum for other reliefs.

Following this order, the complainants decided to appeal against it. The matter was subsequently taken up by the Hon'ble Appellate Tribunal, which, in its order dated 08.04.2022, held the promoter (the developer.) responsible for refunding the amount paid by the complainants, along with interest. The Appellate Tribunal directed the respondent to refund Rs. 16,80,580/- with an interest rate of 10% per annum from 01.01.2018 until the date of payment.

However, the respondent filed a miscellaneous appeal before the Hon'ble High Court, challenging the Appellate Tribunal's order. As a result, the High Court stayed the execution of the order dated 08.04.2022 and instructed the respondent to deposit 20 lakhs within 2 weeks.

Conclusion:

The case filed by Complainant A and Complainant B against the developer. highlights the issues faced by homebuyers in the real estate sector, particularly regarding delayed possession. The complainants sought compensation for the delay in possession as per the agreed-upon timeline. Legal proceedings have been ongoing, with the Rajasthan Real Estate Regulatory Authority, the Appellate Tribunal, and the High Court all involved in the resolution of this case.