In a recent development, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has granted an extension to the developer for their project named the project. The extension application, numbered the extension application, was filed by the Promoter/Developer under section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The project, registered under MahaRERA registration, had faced delays due to a stop work notice issued by the Slum Rehabilitation Authority (SRA), which was subsequently withdrawn. This article delves into the details of the case and the Authority's decision.
Case Background
The project, a redevelopment project under the purview of the SRA, consists of one building known as the sale building. The Promoter, the developer, registered the project with MahaRERA in August 2017, with an initially stated completion date of 31.12.2021. However, the Covid-19 pandemic necessitated multiple extensions for all projects registered with MahaRERA. Notifications/Orders issued on 02.04.2020, 18.05.2020, and 06.08.2021 extended the completion date until 30.12.2022.
The Extension Application
On 15.02.2023, the developer filed an extension extension application seeking an extension of the project's registration from 31.12.2022 to 31.12.2026 under section 7(3) of the said Act. The Promoter highlighted that the project had faced a significant setback due to the issuance of a stop work notice by the SRA on 08.03.2018. Challenging the notice in the Bombay High Court, the Promoter contended that it was issued without proper prior notice. Eventually, on 22.05.2020, the stop work notice was withdrawn, and construction activities resumed in August 2020. The Promoter sought the extension to ensure the project's completion without interruption.
Authority's Decision
The key issue before the MahaRERA was whether to grant the extension under Section 7(3) of the said Act, considering that the Promoter had not obtained majority consents from the Allottees (buyers) of the project, as required. Section 7(3) allows the Authority to impose additional terms and conditions to let the registration remain in force instead of revoking it.
After careful examination, the MahaRERA observed that the primary objective of the said Act is to promote the real estate sector in an efficient and transparent manner while safeguarding the interests of consumers, including home buyers and Allottees. Halting the project by not extending the registration would be detrimental to the consumers' interests, and the Promoter would be unable to undertake necessary actions for efficient completion without registration. Therefore, the Authority decided to grant the extension sought by the developer under Section 7(3).
Conditions Imposed
In granting the extension, the MahaRERA imposed certain conditions to ensure the completion of the project while preserving the rights of the Allottees. The conditions are as follows:
A. Completion Deadline: The Promoter is directed to complete the remaining construction work and obtain the Occupation Certificate (OC) by 31.12.2026. The Allottees are expected to cooperate with the Promoter during this process, while their rights under the said Act remain intact.
B. Reporting and Updates: The Promoter is required to submit quarterly progress reports to the MahaRERA, outlining the status of the project and the steps taken to expedite completion. This will ensure transparency and accountability throughout the extended period.
C. Allottee Grievances: Any grievances raised by the Allottees during the extension period will be promptly addressed by the Promoter in accordance with the provisions of the said Act.
Conclusion
In the case of the developer' the project, the MahaRERA has granted an extension from 31.12.2022 to 31.12.2026, allowing the Promoter to complete the project. The decision was made considering the interests of the Allottees and the objective of promoting an efficient and transparent real estate sector. The extension comes with conditions, including a revised completion deadline, regular reporting, and addressing Allottee grievances. This decision ensures the progress of the project while safeguarding the rights of the consumers.