MahaRERA orders partner promoters to transfer project login credentials for RERA compliance

In Suo Motu Case No. 299 of 2023, MahaRERA directed partner promoters to ensure transfer and confirmation of project login credentials within two weeks so regulatory records could be updated

MahaRERA orders partner promoters to transfer project login credentials for RERA complianceREUNION / INSIGHTSCLARITY / CONTEXT / PERSPECTIVE
Reunion Insights editorial image

In a recent virtual hearing conducted by the Maharashtra Real Estate Regulatory Authority (MahaRERA), a significant case regarding RERA compliance was discussed. The case, numbered 299 of 2023, involved two registered projects. The promoters of these projects, the developer, represented by partners from the developer, were present during the hearing. The primary issue addressed was the provision of login credentials to ensure compliance with the Real Estate (Regulation and Development) Act, 2016 (RERA).

Background of the Case:

The developer, classified as a promoter/developer under the RERA Act, had registered the aforementioned projects under Section 5 of the Act. The promoter firm consisted of eight partners from the developer. The case was listed to resolve the limited issue of providing login credentials for RERA compliance.

Virtual Hearing Proceedings:

The virtual hearing took place on May 15, 2023, and the authority recorded the following proceedings:

  1. the developer's Submissions: The advocate for the developer, representing the promoter, highlighted the background of the matter and the necessity of accessing the login credentials. They emphasized that the login credentials were required to update records and ensure compliance with various RERA regulations. Additionally, they mentioned that an arbitration interim order restrained the other party from obstructing project completion. Allottees were also mentioned as stakeholders in the projects.
  2. the developer's Submissions: The advocate for Chetan Bhanushali and Pravin Chamaria from the developer requested an opportunity to clarify their position to prevent baseless allegations. They stated that they had handed over the login credentials to the promoter firm, the subject of the proceedings. They also expressed the need to present their statement in writing.

Written Submissions and Remaining Issue: Both the developers filed their written submissions. the developer provided the login credentials, indicating their willingness to share them with the developer. However, the developer denied receiving the credentials. The primary remaining issue was to ensure that the developer received the login credentials for the respective projects to maintain RERA compliance.

Final Order:

The final order, signed by Mahesh Pathak, Member 1, MahaRERA, and Ajoy Mehta, Chairperson, MahaRERA, stated the following:

  1. the developer, as the partner promoter, must ensure that the developer receives the login credentials within two weeks from the date of the order.
  2. the developer is required to confirm to the authority that they have handed over the login credentials.
  3. the developer must confirm the receipt of the login credentials.

Conclusion:

The MahaRERA virtual hearing, case number 299 of 2023, addressed the critical issue of providing login credentials to ensure RERA compliance for the registered projects. The order emphasized the responsibility of the developer, as the partner promoter, to deliver the credentials to the developer within a specified timeframe. This ruling aimed to facilitate project progress and compliance with RERA regulations.