MahaRERA extends SRA project to December 2025 with milestone reporting

In Regulatory Case No. 13 of 2023, MahaRERA extended an SRA project's registration to 30 December 2025 despite the absence of majority allottee consent and required milestone plans, monthly reports...

MahaRERA extends SRA project to December 2025 with milestone reportingREUNION / INSIGHTSCLARITY / CONTEXT / PERSPECTIVE
Reunion Insights editorial image

In a recent development, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has granted an extension to the developer for their project, the project. The Promoter had filed an extension application seeking additional time to complete the project, which has been registered under MahaRERA with Registration No. the project's registration. This article provides an in-depth analysis of the case, highlighting the key details and the Authority's decision.

Case Details:

Regulatory Case No.: 13 of 2023

Promoter Name: the developer

Project Name: the project

MahaRERA Project Registration No.: the project's registration

Background:

The Promoter, the developer, is defined as the developer under the Real Estate (Regulation and Development) Act, 2016 (RERA). They had registered the project with MahaRERA, specifying the completion date as 31st December 2021. Due to the Covid-19 pandemic, MahaRERA had previously granted three extensions to all registered projects, extending the completion date until 30th December 2022.

Extension Application:

The developer filed an extension application (No. the extension application) on 4th February 2023, seeking a further extension under Section 7(3) of the RERA Act. The application was heard by MahaRERA on 16th May 2023. The Promoter informed the Authority that the project is a Slum Rehabilitation Authority (SRA) project involving the rehabilitation of approximately 700 individuals. They had already completed the rehabilitation of around 500 dwellers. The project faced litigation that reached the Supreme Court but has now been settled. The Promoter requested an extension until 30th December 2025.

Authority's Decision:

The Authority considered the application and the objectives of the RERA Act, which aim to regulate and promote the real estate sector while protecting the interests of consumers. Although the Promoter did not obtain the majority consents of the Allottees, the Authority recognized the importance of allowing the registration to remain in force to avoid halting the project's progress. Granting the extension would ensure the Promoter can efficiently complete the project while safeguarding the interests of homebuyers.

Extension Granted with Conditions:

The MahaRERA Chairperson, the MahaRERA Chairperson, granted the extension for the project from 31st December 2022 to 30th December 2025. However, certain conditions were imposed to ensure timely completion and transparency:

Completion and Occupation Certificate: The Promoter is required to complete the remaining construction work and obtain the Occupation Certificate (OC) by 30th December 2025. The rights of the Allottees under the RERA Act will remain unaffected.

Milestones and Progress Reports: The Promoter must submit PERT CPM/BAR charts within 15 days of the order, outlining the milestones for project completion. Monthly progress reports, highlighting achieved milestones and any delays, should be submitted to MahaRERA, the Association of Allottees (if formed), and the Allottees themselves.

Regular Updates: Upon receiving the OC, the Promoter must inform MahaRERA and provide periodic updates on the project's registration webpage.

Conclusion:

The decision by the Maharashtra Real Estate Regulatory Authority to grant an extension to the developer for their the project reflects the Authority's commitment to balancing the interests of both developers and homebuyers. By allowing the registration to remain in force with conditions, the Authority ensures the project's progress while protecting the rights of consumers. The imposed conditions will help monitor and track the completion of the project in a transparent manner, promoting efficiency and accountability within the real estate sector.