MahaRERA extends redevelopment project registration to June 2025 with monitoring conditions

In Regulatory Case No. 18 of 2023, MahaRERA extended a substantially completed redevelopment project's registration to 30 June 2025 despite the absence of majority allottee consent, while imposing...

MahaRERA extends redevelopment project registration to June 2025 with monitoring conditionsREUNION / INSIGHTSCLARITY / CONTEXT / PERSPECTIVE
Reunion Insights editorial image

In a recent regulatory case before the Maharashtra Real Estate Regulatory Authority (MahaRERA), the developer sought an extension for their project named "the project." The case, numbered 18 of 2023, involved the rectification of a typographical error in the final order issued on May 18, 2023. Chairperson the MahaRERA Chairperson presided over the virtual hearing held through video conference, and the promoter's counsel represented the Promoter. This article provides a comprehensive overview of the case and its final order, highlighting the key points and implications.

Case Details:

Promoter: the developer

Project Name: the project

MahaRERA registration: registered project

Extension application: filed by the promoter

Final Order:

The final order dated May 18, 2023, pertained to the extension application filed by the developer. The Promoter sought an extension under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The Authority noted that the Promoter had previously obtained three extensions due to the impact of the Covid-19 pandemic.

Key Observations:

The project, the project, is a MHADA redevelopment project consisting of a single building.

The project is substantially completed, but the delay in its finalization is attributed to MHADA, as obtaining permissions and vacating existing residents took time.

The Promoter failed to obtain majority consents from the Allottees of the project for the extension application.

Analysis and Decision:

The Authority deliberated on the extension application under Section 7(3) of the Act. While the Promoter did not secure majority consent from the Allottees, the Authority recognized that the Act aimed to promote the real estate sector transparently and protect the interests of consumers. Refusing the extension would halt the project's progress and negatively impact the consumers.

The Authority, therefore, exercised its discretion under Section 7(3) and decided to grant the extension. The registration of the project was extended from February 1, 2023, to June 30, 2025, with certain conditions. These conditions include the completion of the remaining construction work and obtaining the Occupation Certificate (OC) by the specified deadline. The Promoter was directed to submit a PERT CPM/BAR chart outlining milestones and share it with Allottees and the landowner. Monthly progress reports were also mandated to track the project's development.

Conclusion:

In the case of the developer seeking an extension for the project, the Maharashtra Real Estate Regulatory Authority granted the extension, recognizing the aim of promoting the real estate sector while safeguarding consumer interests. By allowing the project to continue, albeit with conditions, the Authority ensures that completion is achieved efficiently, minimizing the impact on the Allottees. The rectification order corrected a typographical error in the final order, ensuring accuracy in the proceedings.