The Haryana Real Estate Appellate Tribunal upheld a refund order where possession of a residential unit had been delayed and the occupation certificate for the relevant tower remained pending.
Background
The allottee had booked a residential unit with an agreed possession date in July 2019. The source article recorded a booking payment of ₹3,40,000 and total sale consideration of ₹13,07,008.
After possession was not delivered, the allottee approached the Haryana Real Estate Regulatory Authority seeking a refund with interest.
Authority's order
On 7 July 2022, the Authority directed refund of the amount paid together with interest at the prescribed rate, recorded in the source article as 9.70%.
The total refund figure stated in the historical article was ₹17,61,798.
Appeal
The promoter argued that the project was complete and that an application for the occupation certificate for the relevant tower had been submitted in June 2019.
The Appellate Tribunal noted, however, that while other blocks had received occupation certificates earlier, the certificate for the allottee's tower remained pending.
Tribunal's decision
In Appeal No. 51 of 2023, decided on 15 May 2023, the Tribunal upheld the refund relief. It treated the failure to complete the relevant unit and secure the occupation certificate within the promised timeframe as attributable to the promoter on the material before it.
Practical significance
The decision shows that completion claims must be assessed at the level relevant to the allottee's actual unit or tower. An occupation certificate for other parts of a development does not necessarily answer a refund claim where the buyer's own tower remains uncertified and possession overdue.