A Haryana appellate dispute considered compensation after an earlier settlement substituted another unit but the replacement possession was also delayed.

Haryana RERA compensation appeal follows settlement and renewed possession delayREUNION / INSIGHTSCLARITY / CONTEXT / PERSPECTIVE
Reunion Insights editorial image

Appeal No. 150 of 2022 before the Haryana Real Estate Appellate Tribunal concerned compensation following a delayed-possession dispute that had already produced an earlier settlement between the parties.

Original booking and delay

Two allottees had booked commercial space and paid ₹3,07,725 initially. The source record stated that approximately 95% of the overall consideration was ultimately paid, but possession was not delivered within the expected timeframe.

An alternative unit was offered during the dispute.

Settlement and replacement unit

On 4 February 2019, the parties entered into a settlement under which the earlier complaint was to be withdrawn and the allottees would accept a replacement unit in another development.

Possession of the replacement unit was then also delayed, leading to a fresh complaint seeking compensation and other relief.

Adjudicating Officer's award

The Adjudicating Officer awarded compensation for delay at 6% per annum on the deposited amount. The source article recorded total compensation of ₹4,31,918 together with litigation costs.

Issue on appeal

The promoter appealed, arguing that the earlier settlement limited claims relating to the original unit and therefore affected the period for which compensation could be awarded.

The allottees' position was that the settlement itself had not been performed within the agreed timeframe because possession of the replacement unit was delayed.

At the time covered by the historical article, the appeal remained pending and no final appellate outcome had been recorded.

Practical significance

The dispute highlights an important distinction between settling an original possession claim and performing the obligations created by that settlement. A replacement-unit arrangement can resolve one dispute but create new rights and obligations if the substituted possession commitment is itself not met.

Because the historical source described the appeal as pending, this article does not treat the compensation award as finally affirmed or overturned.