Appeal No. 733 of 2022 before the Haryana Real Estate Appellate Tribunal concerned delayed possession in an affordable-housing project and the promoter's reliance on force-majeure circumstances.
Background
An allottee had booked an apartment under Haryana's Affordable Group Housing Policy. The buyer agreement set out a possession timeline and payment obligations.
After possession was delayed, the allottee approached the Haryana Real Estate Regulatory Authority. The promoter relied on circumstances including the COVID-19 pandemic and pollution-control restrictions as explanations for the construction delay.
Issues raised
The dispute brought several recurring RERA questions into focus:
- how contractual possession timelines interact with the regulatory framework;
- when force-majeure events can justify additional time;
- the relevance of environmental clearances and government restrictions; and
- the interest consequences of delayed possession under Section 18 of the Real Estate (Regulation and Development) Act, 2016 and the Haryana rules.
Force majeure and construction delays
The pandemic affected construction through labour shortages, movement restrictions and supply-chain disruption. Pollution-control directions can also interrupt construction activity.
Those circumstances may be relevant to a promoter's explanation for delay, but their legal effect depends on the applicable agreement, regulatory extensions and the period actually affected by the event.
Practical significance
The appeal illustrates why delayed-possession disputes cannot always be resolved by looking only at the original promised date. Regulators and appellate bodies may also need to consider legally recognised extensions and the connection between a claimed force-majeure event and the actual period of delay.
For promoters and allottees, contemporaneous records of approvals, construction restrictions, regulatory extensions and possession commitments can therefore become important when delayed-possession relief is assessed.