A Haryana Real Estate Appellate Tribunal appeal considered how delayed-possession interest should be calculated for a commercial unit where the allottee continued making payments after the contractual possession date.
Background
The unit was allotted in a Gurugram commercial project under an agreement dated 24 December 2010. Possession was due on 24 September 2013. The basic sale price was ₹42,58,735, and ₹39,75,029 had been paid by June 2013.
Possession was offered in January 2018, together with a further payment demand. The allottee approached the Haryana Real Estate Regulatory Authority seeking delayed-possession interest.
Authority's order
The Authority directed the promoter to pay delayed-possession interest at the prescribed rate for the period between the contractual due date and the offer of possession. It also initiated separate action concerning project registration.
Issue on appeal
In Appeal No. 101 of 2020, broader technical objections were not ultimately pressed. The remaining issue concerned how interest should be calculated on amounts paid after the original possession due date.
Tribunal's decision
The Appellate Tribunal distinguished between payments made before and after the due date:
- payments made before 24 September 2013 were to carry delayed-possession interest from that date; and
- payments made afterward were to carry interest from their respective payment dates.
The appeal was partly allowed to give effect to that calculation.
Practical significance
The ruling shows that delayed-possession interest can depend on the timing of individual instalments. It also demonstrates that, once broader jurisdictional objections fall away, the calculation methodology itself can become the decisive appellate issue.