In a recent case before the Haryana Real Estate Appellate Tribunal, the developer filed an appeal against an order passed by the Haryana Real Estate Regulatory Authority. The case involved a complaint filed by Complainant A, a resident of Gurugram, against the developer, a real estate developer. The complaint sought compensation for delayed possession of a property in the Emerald Floors at the project in Gurugram.
Background:
The complaint stated that Complainant A had purchased a unit in the aforementioned project from the original allottees. However, the developer. failed to deliver possession of the property within the agreed timeframe, resulting in a delay of more than four and a half years. The complainant demanded interest for the delayed period of possession as per the provisions of the Real Estate (Regulation and Development) Act, 2016.
the developer is a real estate developer principally engaged in promotion, construction, development and sale of integrated townships, residential and commercial multi storied buildings, houses, flats, shopping malls, hotels, and other developments. the developer was founded and incorporated in 1997 by Mohamed Alabbar
Impugned Order and Appeal:
The Haryana Real Estate Regulatory Authority disposed of the complaint and directed the developer to pay interest at the prescribed rate for the delay in possession. The authority also directed the complainant to pay any outstanding dues after adjusting the interest. the developer. appealed this order before the Haryana Real Estate Appellate Tribunal.
Arguments:
During the appeal hearing, the developer.'s counsel argued that the subsequent allottee (Complainant A) was aware of the project's delayed status when purchasing the property. They contended that the interest should be calculated from the date the subsequent allottee acquired the property, as per a Supreme Court judgment in Wing Commander Arifur Rahman Khan v. the developer.
Decision:
After considering the arguments, the Haryana Real Estate Appellate Tribunal examined the facts of the case. The tribunal noted that the original allottees had booked the property and subsequently sold it to Complainant A. They also observed that the due date for possession had already passed when the subsequent allottee acquired the property. Relying on a recent Supreme Court judgment in the developer. v. Charanjeet Singh, the tribunal rejected the argument that interest should be calculated from the date of acquisition by the subsequent allottee.
Conclusion:
The Haryana Real Estate Appellate Tribunal upheld the impugned order of the Haryana Real Estate Regulatory Authority, directing the developer to pay interest at the prescribed rate for the delayed possession period. The decision clarified that interest for subsequent allottees should be calculated from the due date of possession and not from the date of acquisition. This case serves as an important precedent for similar disputes in the real estate sector, providing clarity on the calculation of interest for delayed possession.