Haryana appellate tribunal dismisses appeal after finding project ongoing under RERA

In Appeal No. 33 of 2021, the Haryana appellate tribunal held that a project whose completion certificate was issued after RERA commenced remained an ongoing project subject to the Act

Haryana appellate tribunal dismisses appeal after finding project ongoing under RERAREUNION / INSIGHTSCLARITY / CONTEXT / PERSPECTIVE
Reunion Insights editorial image

In a recent case before the Haryana Real Estate Appellate Tribunal, the developer appealed against an order issued by the Haryana Real Estate Regulatory Authority. The order was in response to a complaint filed by Complainant A, an allottee of a flat in a project developed by the developer. This article, we will provide a simplified explanation of the case and its key aspects.

Background:

Complainant A had booked a flat in the project in Faridabad, Haryana, and had already made partial payments. The agreement stated that possession of the flat would be given within a specific timeframe. However, the developer delayed the possession and demanded additional payments from Complainant A. Disputing the demands, Complainant A filed a complaint with the Haryana Real Estate Regulatory Authority.

About the developer

The respondent is a corporate real-estate promoter.

The Impugned Order:

The Haryana Real Estate Regulatory Authority disposed of the complaint and issued certain directions. It instructed the developer to withdraw a particular demand since the matter was already sub judice (pending before the court). However, if the court ordered that the amount was payable, Complainant A would have to pay it.

The Authority also directed Complainant A to pay the remaining outstanding amount within a specified time frame, along with interest and delay compensation. Additionally, the developer was instructed to hand over physical possession of the flat to Complainant A upon clearance of dues.

The Appeal:

The developer, dissatisfied with the Authority's order, appealed to the Haryana Real Estate Appellate Tribunal. the developer' main contention was that their project was already completed and sold out before the Real Estate (Regulation and Development) Act 2016 (the Act) came into force. Therefore, they argued that the provisions of the Act should not apply to their project.

The Tribunal's Decision:

After considering the arguments from both sides, the Tribunal examined whether the project fell within the definition of an ongoing project as per the Act. They noted that the completion certificate for the project was issued after the enforcement of the Act. Based on this, the Tribunal concluded that the project was indeed ongoing, and thus, the provisions of the Act were applicable.

Conclusion:

In the appeal filed by the developer, the Haryana Real Estate Appellate Tribunal dismissed the appeal and upheld the Authority's order. The Tribunal emphasized that the project qualified as an ongoing project under the Act, as the completion certificate was issued after the Act came into force. Therefore, the jurisdiction of the Authority to adjudicate the complaint was justified.

This case serves as a reminder that the Real Estate (Regulation and Development) Act 2016 aims to protect the rights of homebuyers and regulate the real estate sector. Developers must comply with the provisions of the Act, even if their projects were initiated before the Act's enforcement. The decision by the Haryana Real Estate Appellate Tribunal reinforces the importance of adhering to the regulations and obligations set forth in the Act to ensure a fair and transparent real estate market.