A six-bungalow residential project in Tandulwadi, Baramati is planned for completion on 31 December 2027.
Location Details:-
Pune is a city in the western Indian state of Maharashtra. It is the eighth most populous city in India and the second largest in the state. Pune is known for its educational institutions, information technology (IT) industries, and automobile industry. The city is also a popular tourist destination, with many historic sites and cultural attractions.
Pune is a popular city for real estate investment and development, with a growing demand for residential and commercial properties. Known for its affordable housing and good infrastructure, Pune offers a wide range of options for buyers and investors in its vibrant real estate market. The city has seen significant growth in recent years, making it an attractive location for real estate development.
Developer
The project is being developed by a real-estate partnership.
Land arrangement
The project land is held under a share arrangement with a private landowner.
Technical Details
The project site is in Tandulwadi, Baramati. It comprises one approved wing on a plot area of 521.02 sq mts, with total approved build-up area of 812.82 sq mts. The source records recreational open space and states that municipal approval was pending.
Building details of the project:-
The Maharashtra Real Estate Regulatory Authority (RERA) has approved the project for a three-story building with no podium. The project has six bungalow apartments, but there is no parking for these residences as per the current update.
the project consists solely of bungalows with varying carpet areas and unit sizes. The space for each unit ranges from 105.64 to 106.80 square meters.
Specific information about the project units is provided in the information below:-
| Sr.No. | Apartment Type | Carpet Area (in Sqmts) | Number of Apartment | Total |
|---|---|---|---|---|
| 1 | Bungalow | 105.64 | 5 | 528.2 |
| 2 | Bungalow | 106.8 | 1 | 106.8 |
Current work status of the project as per MahaRERA:-
As of 18th of November, the construction work for the project has not yet been started.
Facilities and amenities:-
The project includes features such as water conservation, rainwater harvesting, electrical meter rooms, substations, water supply systems, sewerage facilities (including chambers, lines, septic tanks, and STPs), and street lighting.
Project team
The project team includes architecture, engineering, accountancy and construction professionals.
Litigation Details:-
As of now, there are no legal disputes or cases associated with this project.